01 / PROJECTS
Projects
Jobs as they were recorded: what the belt was, what we did, how long the line was down. Client names are used with permission.
FEATURED RECORD · 2026-014
Steel-cord recovery,
cement plant, Perak.
BELTST1000 · 1400 MM
SCOPEHOT VULCANISED
DOWNTIME4 H 10 MIN
02 / RECORD INDEX
REFSITE & SCOPEBELTMETHODDOWNTIME
2026-014CEMENT PLANT, PERAK — KILN FEED RECOVERYST1000 · 1400 MMHOT VULCANISED 4 H 10 MIN
2026-009LIME WORKS, PERAK — SHUTDOWN RE-BELTEP630/4 · 800 MMHOT VULCANISED PLANNED
2025-142QUARRY, SELANGOR — LOADING POINT REBUILDEP500/4 · 650 MMMECHANICAL PLANNED
2025-118PORT TERMINAL, PENANG — SHIP LOADER JOINTST1000 · 1400 MMHOT VULCANISED 6 H 40 MIN
2025-097CEMENT PLANT, PERAK — PULLEY RE-LAG ×4TUFFLAG-CCOLD BOND PLANNED
03 / RECORD IN FULL · 2026-014
The call came in at 22:40 with the kiln feed belt torn across a third of its width. Crew and press left Ipoh at 23:20 with belt from stock.
Joint cut, prepared and pressed on site; the line ran again at 02:50. The joint was logged against the belt number for the next inspection.
FIG — FEATURED RECOVERYNight splice under work lamps — the 4h10m steel-cord recovery.